M
mjkahn
I have a scenario like this:
Task 1. Starts 2/1/06. Resource R1 works on it for 5 days, so it ends on
2/7/06.
Task 2. Dependency (FS) on Task 1, so it starts on 2/8/06. It must be
finished by 2/14/06, which is 5 working days away. Resource R1 will work on
it for 1 day and Resource R2 will work on it for 2 days. Even though there
are 5 days available to work on this task, only 3 days of effort will go into
it.
When I set up my tasks and resources as described above, Project moves the
start date for Task 2 to 3 days before the Finish By date, leaving a gap
between the FS link from Task 1 and the start date. I'd like my Project's
Gantt chart to show that there are 5 possible days on which Task 2 could be
worked, even though there are only 3 days of effort going into it? Is that
possible?
FWIW, I'm using Project 2000.
Thank you!
MJ.
Task 1. Starts 2/1/06. Resource R1 works on it for 5 days, so it ends on
2/7/06.
Task 2. Dependency (FS) on Task 1, so it starts on 2/8/06. It must be
finished by 2/14/06, which is 5 working days away. Resource R1 will work on
it for 1 day and Resource R2 will work on it for 2 days. Even though there
are 5 days available to work on this task, only 3 days of effort will go into
it.
When I set up my tasks and resources as described above, Project moves the
start date for Task 2 to 3 days before the Finish By date, leaving a gap
between the FS link from Task 1 and the start date. I'd like my Project's
Gantt chart to show that there are 5 possible days on which Task 2 could be
worked, even though there are only 3 days of effort going into it? Is that
possible?
FWIW, I'm using Project 2000.
Thank you!
MJ.