D
Dale
Each week I need to create a consolidated plan consisting of ~45 subprojects
to generate a report. The problem is that a couple subprojects use
non-standard calendars. For their individual projects, tasks default to the
non-standard calendar they have defined for their project, however, when I
insert it into the consolidated plan using the Standard calendar, the tasks
default to the Standard calendar and the dates are changed. I know that if
the Project Manager's assign the non-standard claendar to each task the
consolidated plan will match theirs but they do not want to go into each task
and assign the calendar. Is there another way arond this problem?
to generate a report. The problem is that a couple subprojects use
non-standard calendars. For their individual projects, tasks default to the
non-standard calendar they have defined for their project, however, when I
insert it into the consolidated plan using the Standard calendar, the tasks
default to the Standard calendar and the dates are changed. I know that if
the Project Manager's assign the non-standard claendar to each task the
consolidated plan will match theirs but they do not want to go into each task
and assign the calendar. Is there another way arond this problem?