C
Carlos Ortigoso
Hi, friends.
I have a big project with many resources. Everything is working well, but I
have some days when there is no work assigned to a resource. This occurs
because the links among tasks and assignments of the resources.
No problem, it works fine, but I need to view those non-work days of the
resources.
Is there a way to generate a report or a graphic that show me that, i.e, I
need a view like Resource Usage or Resource Graph that show me the days when
the resource have no work assigned to him. Is that possible?
I've tried to make a filter, but I do not know what field to check. Help me,
please.
Thanks in advance,
Carlos
I have a big project with many resources. Everything is working well, but I
have some days when there is no work assigned to a resource. This occurs
because the links among tasks and assignments of the resources.
No problem, it works fine, but I need to view those non-work days of the
resources.
Is there a way to generate a report or a graphic that show me that, i.e, I
need a view like Resource Usage or Resource Graph that show me the days when
the resource have no work assigned to him. Is that possible?
I've tried to make a filter, but I do not know what field to check. Help me,
please.
Thanks in advance,
Carlos