Non-work days of a resource

  • Thread starter Carlos Ortigoso
  • Start date
C

Carlos Ortigoso

Hi, friends.

I have a big project with many resources. Everything is working well, but I
have some days when there is no work assigned to a resource. This occurs
because the links among tasks and assignments of the resources.

No problem, it works fine, but I need to view those non-work days of the
resources.

Is there a way to generate a report or a graphic that show me that, i.e, I
need a view like Resource Usage or Resource Graph that show me the days when
the resource have no work assigned to him. Is that possible?

I've tried to make a filter, but I do not know what field to check. Help me,
please.

Thanks in advance,

Carlos
 
M

Mike Glen

Hi Carlos,

Welcome to this Microsoft Project newsgroup :)

Try the Resource Graph and right click in the graph and select Remaining
Availability. Ditto with the Resource Usage view.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
J

John

Carlos Ortigoso said:
Hi, friends.

I have a big project with many resources. Everything is working well, but I
have some days when there is no work assigned to a resource. This occurs
because the links among tasks and assignments of the resources.

No problem, it works fine, but I need to view those non-work days of the
resources.

Is there a way to generate a report or a graphic that show me that, i.e, I
need a view like Resource Usage or Resource Graph that show me the days when
the resource have no work assigned to him. Is that possible?

I've tried to make a filter, but I do not know what field to check. Help me,
please.

Thanks in advance,

Carlos

Carlos,
Is it possible? Definitely. Is it easy to generate such a report? Well,
that depends. If you want a report that shows only those days when a
resource has no assignments, you will probably need to use an advanced
feature of Project, namely VBA. However, if you don't mind seeing data
that gives days of total availability along with partial days you can
use one of two approaches.

For a report, try the built-in report (View/Reports/Workload/Resource
Usage). Edit the report to show the Remaining Availability field. For a
graph, use the Resource Graph. Again display the Remaining Availability
(Format/Details).

Hope this helps.
John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top