D
dtimoce
Hello
I'm having this buggy problem in MSP 2003: i have several tasks that
include some non-working days ( end of this year and begining of the
new year). I see the non-working time ( selected in the project's
calendar ) greyed in the gantt-chart view, but the tasks durations are
not taking into account these non-working days ?
Anyone seen this kind of problem before and has an workaround ?
Thanking you in advance
Regards
D TIMOCE
I'm having this buggy problem in MSP 2003: i have several tasks that
include some non-working days ( end of this year and begining of the
new year). I see the non-working time ( selected in the project's
calendar ) greyed in the gantt-chart view, but the tasks durations are
not taking into account these non-working days ?
Anyone seen this kind of problem before and has an workaround ?
Thanking you in advance
Regards
D TIMOCE