Non-working time in the Resource Graph

A

Andy Bruncke

I am having 2 issues with seeing non-working time in the Resource Graph
view:

1. Why can I not set non-working time to display in this view, even just
the default calendar non-working time?
2. Is there any way I can display non-working time for the resource I have
selected?

I often use the split Gantt view with the resource graph on the bottom to
help me level people manually, and it would really help to see their
non-working time so I know that the big gap of time is there for a reason,
and not because I did something bad. :)

Thanks


Andy
 
J

Jan De Messemaeker

Hi,

No way, I'm sorry.
Some of my customers do not enter absence days in the calendar but enter
fixed date tasks instead, using resource leveling to make other tasks move.
There is an article on that on my website
HTH
 

Ask a Question