ellebelle said:
Hi John,
Thanks for running with me on this.
In answer to your questions:
1. Does your project have a baseline set?
No
2. How many tasks are like this in your plan?
239 tasks run over teh christmas period. They all have splits.
3. Are the tasks with splits linked to successor tasks?
No links at all in the project
4. Do the tasks with splits have actuals?
No
5. Are you using earned value metrics?
I don't think so. I am not entirely sure what this is.
I hope this makes it a lot easier!
Thanks,
Ellen
Ellen,
OK, interesting, especially the answer to question 4. What I meant by
"actuals" is anything that shows what actually happened during that
period. Since you are talking about last Christmas I would expect to see
all tasks spanning the holiday break have some amount of progress (i.e.
they were actually started - maybe some were actually completed). If
there are no "actuals" then I wonder why the schedule even exists.
If you do not have a baseline, then you are not using earned value
metrics. Earned value metrics are things such as: BCWS (Budgeted Cost of
the Work Scheduled), BCWP (Budgeted Cost of the Work Performed), ACWP
(Actual Cost of the Work Performed, SPI (Schedule Performance Index) and
CPI (Cost Performance Index). You can read more about earned value
metrics in the Project Help file.
Also with no links I wonder what the schedule is describing. I can't
think of any real world project that doesn't have a series of activities
(tasks) that aren't linked in some way. For example, before you paint a
room, the walls must be prepared. Before a software application is
released, it must be developed and tested. And so forth. It sounds like
the whole project is made up of activities wherein someone manually
entered start and finish dates based on who knows what. That is NOT the
way to build a project plan, at least not with MS Project.
Now, it probably sounds like I'm railing on you big time but my intent
is truly to help and one way to do that is to make sure you understand
how Project can help you manage your project.
OK, where do we go from here. I could probably lead you through a
process to clear out the task splits, but from your answers to my
questions I think we need to do a lot more to get you squared away.
First, I suggest you go to our MVP website at:
http://www.mvps.org/project/links.htm
and take a look at fellow MVP, Mike Glen's series on Project lessons and
techniques. I think that will help you immensely in understanding the
basics of Project Management and how to use Project more effectively.
Second, would it be possible to e-mail me your file? That would allow me
to better understand what you really have and if it is salvageable, I
could also remove the splits. If your file has sensitive information
(e.g. task names, cost data, etc.) I can send you a macro to desensitize
it. A similar macro can also be found on fellow MVP, Jack Dahlgren's
website at:
http://masamiki.com/project/macros.htm
Jack's marco is called "scrub".
Let me know what you want to do. If you want you can contact me direct
at my address below.
John
jensenj6atatcomcastdotdotnet
(remove obvious redundancies)