D
Don Conrad
Hi,
I'm setting up a schedule and have run into an issue that is a first for
me and was not able to figure it out.
Portions of my project will be working 5 day weeks, some portions
working 6 day weeks, and one that will actually be doing 7 day weeks.
Is there a way to specify by task what the non-working time will be? I
tried highlighting it and making the updates but it applied the settings
throughout the project. Any help would be appreciated.
Don
I'm setting up a schedule and have run into an issue that is a first for
me and was not able to figure it out.
Portions of my project will be working 5 day weeks, some portions
working 6 day weeks, and one that will actually be doing 7 day weeks.
Is there a way to specify by task what the non-working time will be? I
tried highlighting it and making the updates but it applied the settings
throughout the project. Any help would be appreciated.
Don