task will take how ever long it takes to complete exactly that deliverable,
nothing more and nothing less. You can't stop when the defined deliverable
is 90% complete and it's pointless to continue work beyond the point it is
100% complete. Thus each task has a specific, concrete, exactly measurable
amount of work associated with it. Work costs X dollars per unit - you have
to pay resources to do work or they don't show up and nothing happens. You
pay them a specifc rate or salary. So the cost of doing the work on a task
is defined by the amount of work required to create the deliverable which in
turn is defined by the nature of the deliverable itself. As a result, you
cannot define the budget until you have explicitly defined the tasks,
analysed how much work will be involved in each one, and identified the
human and material assets that will be doing that work and their associated
costs.
If the projected cost is greater than the assets on hand, you cannot
arbitrarily shrink durations to fit - instead you must redefine the
project's objectives to encompass reduced deliverables. As an example, if
my painter paints 10 square feet per hour and we have 1000 square feet of
wall to paint, it will take him 100 hours. If we can't afford to pay for
100 hours, we can't just pull out of thin air that he will do it in 75
hours. The only way we can really get the budget down to within the
resources we have available is erect fewer walls so he only has to paint 750
square feet.
HTH
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
nitsa said:
I tried what you suggested as a sample on one task:
I defined a resource called "cost" in the resource sheet and gave it a
standard rate of $1/hr.
I assigned this resource to the task of which duration was 10 and in the
"assignment information" I defined a bell shape work contour. The outcome
cost was $40.
If I wanted the cost to be a 100, the duration would increase to 25. And
since my planned duration and planned budgets are both given to me as an
input from "outside", all I could do is to change the rate. Am I working
with
the right program?
I entered an activity, gave it a start date and a duration of 10 days. I