Not showing links to milestones on gantt chart

P

PJH

I am using MSP 2002 and on the gantt chart would like to display the
dependency links between tasks, but not milestones.

I do not want to delete the links, I just don't want them to show as I have
listed my milestones at the top rather than within the plan.

Is this possible?
 
G

Gérard Ducouret

Hello, PJH,
Possible but not immediate.
For all the tasks which are predecessor for this milestone, double the Bar
Style with a white symbole (with exactly the same shape) placed just above
the standard bar symbol.
For the milestone itself, do the same thing : a white symbole just above the
black symbol
Format / Bar styles...

Gérard Ducouret
 