Z
Zazoo
Hi,
I would like to schedule several projects at the same time for one resource.
Actually, the first project consists in preparing calculations on a computer,
so it takes maybe 2 or 3 hours every 3 days. Once a calculation is launched,
the resource can do the second project. As soon as a calculation is finished,
my resource needs to post-process the results and prepare the following
calculation. Then the resource can go back to the second project. My problem
is when I have a 2 hours task for the project 1 on one day, Microsoft Project
does not schedule anything else for the same day. So there are some days when
my resource is supposed to work 2 hours instead of 8...
Thank you
I would like to schedule several projects at the same time for one resource.
Actually, the first project consists in preparing calculations on a computer,
so it takes maybe 2 or 3 hours every 3 days. Once a calculation is launched,
the resource can do the second project. As soon as a calculation is finished,
my resource needs to post-process the results and prepare the following
calculation. Then the resource can go back to the second project. My problem
is when I have a 2 hours task for the project 1 on one day, Microsoft Project
does not schedule anything else for the same day. So there are some days when
my resource is supposed to work 2 hours instead of 8...
Thank you