I'm a contractor and I provide support as needed for the entire length of the
contract (1 year). I have a task called 'General Admin Support'. I made the
task duration 1 year and assigned myself as a resource. Now Project puts 8
hours a day in the work column for the entire duration of this task. Now I'm
not working on this task every day, in fact some days I might be working 6
hours and others maybe only 10 minutes. How can I reflect this in the task?
Or should I set up tasks like that differently?