Order of tasks

B

BC

I'm trying to enter in codes for the tasks and duration patterns. What is
the order that this should be placed in? Outline Code, then Group Codes,
then duration or should duration be the first action?

Thank you,

BC
 
J

Jan De Messemaeker

Hi BC,

Outline and Group codes do not influence schedule at all, so theuy may be
entered whenever it suits you.
HTH
 
B

BC

Jan De Messemaeker said:
Hi BC,

Outline and Group codes do not influence schedule at all, so theuy may be
entered whenever it suits you.
HTH

--
Jan De Messemaeker
Microsoft Project MVP
http://users.online.be/prom-ade



Hello Jan,

I'm new to this software and was working on a project that was due yesterday
and still having problems. I appreciate your help....I just need a step by
step beginner instruction guide to this program. I work in with an IT group
as an admin and it can be challenging.

Thanks again,
Barbara
 
J

Jan De Messemaeker

Don't worry Barbara and definitely don't be disappointed when my comments
are a little "short"... I'm in reality a very lazy man and I don't like
typing much so my shoort messages may sound harsh, wheread they aren't meant
to.

Keep on asking if necessary!
 
M

Mike Glen

Hi BC,

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top