Outline Level Issues

G

Ginger

Hi All,

I have a very large project plan that is 9 outline levels deep.. Has anyone
experienced any issues with that many nests? I am having some difficulties
with calcuations and I am not sure if this is the cause or if anyone has had
any issues.

Thanks, Ginger
 
R

Rod Gill

The only known issue is with Project 2003 where you can't outdent again.
That problem is fixed by SR1. No issues re calculations that I know of.
Provided there are no circular relationship errors on the status bar and you
have calculation set to automatic, all totals should be correct.

What problem are you experiencing?
 
C

Catfish Hunter

I once had a problem with a project calculating. It turned out I had made a
logic tie to one of my summary task. Removed the tie and it was fixed.
 
G

Ginger

Hi Rod, I had put this question in a different posting but I am not sure
that project is not calculating it correctly. I may not understand why MSP
is calculating it this way...

I am also having trouble trying to understand why project is doind the
follwoing which I think is related to my gantt chart troubles..

**Summary Task1 is the overall summary. Summary 1A - 1D are summary tasks
under Summary Task 1.. What I am not understanding is why would the
Summary Task 1A have a higher Actual Duration then Summary Task 1 when
Summary Task 1 is the "parent"?

% Comp Duration Act. Dur Rem. Dur
65% Summary Task 1 251.5 days 163.49 days 88.01 days
96% Summary Task 1A 180 days 173.58 days 6.42 days
0 Summary Task 1B 11 days 0 days 11 days
0 Summary Task 1C 10.5 days 0 days 10.5 days
0 Summary Task 1D 40 days 0 days 40 days
 