B
Barb PMO
My company is using current versions of MS Project and Project Server. A few
Outlook users have installed the Outlook integration add-in and I am
currently testing the import functionality.
1. Why are imported tasks displayed in the Outlook calendar and not in the
Outlook task list? I think if I understood why it was done this way, I would
be able to work with it - maybe
2. The reason I say maybe is because one Project task imports a new calendar
item daily on my outlook calendar (which makes my calendar unreadable). Is it
a setting in Project that's making it do that, or is it how I am scheduling
the Work? For example, for a 4 hours of work for a resource, I will place a 4
in that resources month "cell" (using the Usage table).
3. Thirdly, why are tasks marked as 100% complete (in project) still
importing into my calendar?
Outlook users have installed the Outlook integration add-in and I am
currently testing the import functionality.
1. Why are imported tasks displayed in the Outlook calendar and not in the
Outlook task list? I think if I understood why it was done this way, I would
be able to work with it - maybe
2. The reason I say maybe is because one Project task imports a new calendar
item daily on my outlook calendar (which makes my calendar unreadable). Is it
a setting in Project that's making it do that, or is it how I am scheduling
the Work? For example, for a 4 hours of work for a resource, I will place a 4
in that resources month "cell" (using the Usage table).
3. Thirdly, why are tasks marked as 100% complete (in project) still
importing into my calendar?