Outlook - Project Task Form change

R

Richard B

Has anyone an idea of why our project tasks have changed?

They used to look like this : http://ulterium.com/project_task_1.gif
But now they change to look like this : http://ulterium.com/project_task_2.gif

There’s also no button for going to “Go to my work’â€, so we are unable to
extend the finish date for a task if needed.

We checked the “Time sheet settings and default†and/or “Tasks settings and
display†in “Server settings†on PWA, but without finding an answer.

Thank you for anyone that can help.

Richard
 
M

Mike Glen

Hi Richard,

As John said: try posting on the microsoft.public.project.server newsgroup.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm. That newsgroup is where the server gurus
hang out. Please remember that all responders are volunteers - you'll need
patience until someone has the time to respond.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top