A
Alain R.
Hi,
I'm currently working on some personal application development in spiral.
Therefore i would like for the first spiral round to use MS Project in
the following way :
- on 01.01.2006, Analysis : 2 hours
- on 03.01.2006, Analysis : 4 hours
- on 14.02.2006, Planning : 10 minutes
and so on...
i want to type in MS Project the amount of hours worked and the concrete
dates. Like that after the first spiral round i will have an overview of
a full development cycle, that i will use and improve for the
next,...and so on..
How can i tell to MS Project that on 01.01.2006 i work only 2 hours
without changing any % resource use, or other stuff like that ?
thanks a lot,
Alain R.
I'm currently working on some personal application development in spiral.
Therefore i would like for the first spiral round to use MS Project in
the following way :
- on 01.01.2006, Analysis : 2 hours
- on 03.01.2006, Analysis : 4 hours
- on 14.02.2006, Planning : 10 minutes
and so on...
i want to type in MS Project the amount of hours worked and the concrete
dates. Like that after the first spiral round i will have an overview of
a full development cycle, that i will use and improve for the
next,...and so on..
How can i tell to MS Project that on 01.01.2006 i work only 2 hours
without changing any % resource use, or other stuff like that ?
thanks a lot,
Alain R.