I am using Project to summarize four different project files. I have inserted
each project file and want to use Project to summarize specific tasks from
the four inserted project files. I use the copy and paste as a link option
for each task that I want to bubble up, but not all of the data is accurate.
Some tasks that are bubbled up link fine and as the duration, start and end
dates change in one of the original four project files change the bubbled up
link changes as well. But for others the start and end dates are incorrect
and appear to be incorrectly linking to the wrong task in the original four
project files. Does anyone know a way to resolve this?
Thanks,
Mike
each project file and want to use Project to summarize specific tasks from
the four inserted project files. I use the copy and paste as a link option
for each task that I want to bubble up, but not all of the data is accurate.
Some tasks that are bubbled up link fine and as the duration, start and end
dates change in one of the original four project files change the bubbled up
link changes as well. But for others the start and end dates are incorrect
and appear to be incorrectly linking to the wrong task in the original four
project files. Does anyone know a way to resolve this?
Thanks,
Mike