I'm using Project 2003 Standard and have a master project with subprojects.
The subprojects have pasted links from an Excel spreadsheet. When I open the
master project it does not update the subproject links. Additionally, the
Edit->Links selection is grayed out. How do I update the subproject links
without having to open each and every subproject individually (there are 10
of them so it will be very tedious if this is the only solution).
Thanks,
Daniel
The subprojects have pasted links from an Excel spreadsheet. When I open the
master project it does not update the subproject links. Additionally, the
Edit->Links selection is grayed out. How do I update the subproject links
without having to open each and every subproject individually (there are 10
of them so it will be very tedious if this is the only solution).
Thanks,
Daniel