percent complete equal to today

P

pahuntr

I have daily ongoing training that started weeks ago. It has actual end date. Is it possible to show and have the % complete adjust everyday automatically?
 
J

John Beamish

You will have to make two clicks.

1. Click on the task
2. Click on the "Update as Scheduled" button which is on the Tracking
toolbar.

JLB, PMP


pahuntr said:
I have daily ongoing training that started weeks ago. It has actual end
date. Is it possible to show and have the % complete adjust everyday
automatically?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top