Phone number to call

S

Shaun

I have some questions about re-baselining some tasks that have had a scope
change. I have tried writing them in this forum but have not gotten an
answer that has worked. Is there someone I can call?

Thanks,

Shaun
 
S

Steve House [Project MVP]

You have had several answers, Shaun. Why do you say they haven't worked?
From what little information you have provided it appears that the problem
lies in the way you have set up your work breakdown. If you fix that, the
problem will go away. If that's not the solution, provide more detailed
information about your situation and we'll try to help.

Note that this forum is not operated by nor moderated by Microsoft and is
not part of their tech support group. Those of us who are designated MVP
are all volunteers, not employed by MS, who freely give of our time and
expertise to help users such as yourself. Free phone support is just not in
the cards.
 
S

Shaun

Steve, I meant no disrespect. I have found this forum extremely helpful not
only in answering questions that I have posed but reading other's questions
as well. However to try and explain here all that is going on when I try to
re-baseline my project is just too much. I was able to speak to my trainer
from COMPUSA where I took a course 2 years ago and by re-readeing the chapers
on baselines and interim baselines in my "Using Project 2000" book. What I
want to do with my baseline is not something that Project likes to do, and in
all honesty, I agree that once a baseline is set that is it. It is my
Manager who may want this done. I have figured out a way to adjust my
baseline though it will be labor intensive, by removing the actual hours I
have entered, clearing the original baseline, adjusting it, resetting it, and
then re-entering my actuals.

Again, I was not trying to throw stones when I said that the answers I got
previously did not work and I do greatly appreciate the help that I have
gotten from here.

Shaun
 
S

Steve House [Project MVP]

But what is wrong with splitting the task into smaller tasks, one task for
each resource assigned to it? That way it become a no brainer to update the
baseline for the one resource's work if this is one of those odd cases where
it is required?

The way I explain it to my classes, consider where a computer classroom
needs to be painted. If the painter and his assitant are going to be the
ones to disconnect and move the computers, move out the furniture, take
fixtures off the wall, blend the colour, and apply the paint, then move
everything back in again, you can show it as one task "paint the room" and
assign the painter and assistant to it. But if some techs from IT are going
to disconnect the computers, labourers from maintainance come in to move the
furniture, a carpenter to take down the wall fixtures, a colour specialist
to blend the paint, plus the painter and his assistant to apply the paint,
you need to break it down into all its separate component activities so each
one can be scheduled as a distinct task. From the way you present your
problem it sounds like you have a task listed as a single task like in the
first case but resources who actually do different things assigned to it
like the second. I strongly suspect that is the root of your problem. If
there are 5 resources assigned to that task, you need to split it into 5
different tasks, one for each resource, perhaps grouped together as subtasks
under one summary task. If you do that, it's extremely simple to rebaseline
the one task/resource out of the group that has changed.

Your project task list isn't complete until it details every individual
specific physical activity performed by a single "skill package."


--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
 
K

Karen M

Shaun,

There is a BUG in Project 2002 and 2003 whereby baselining selected tasks
does NOT calculate right. Our company has gotton a hotfix for Project 2003
and at that time Microsoft was NOT sure whether or not they were going to
implement into 2002. Below is the link to the hotfix. To baseline change of
scope items highlight the task you want and select Tools, Tracking, Save
Baseline. Check the Selected Tasks check box and check the first item only -
To all Summary Tasks. Here is the link to the hotfix that fixes the selected
tasks calcuation issue for Project 2003 -
http://support.microsoft.com/?kbid=891203
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top