J
j8chan
Hi
I've been trying to find a solution to my problem for a few days now. For
example, i have 8 people and 4 work stations, two people work with one
station so it becomes 4 teams.
i would like to level on both the pool of resources and the pool of work
stations but they have to by working together at the same time, I had two
tasks with each resource but it wouldn't schedule properly (ie a station
working without people at it). If one work stations goes down, then 2 people
can work on another different task for that resource pool.
Please help, could the answer lie in the task duration, fixed units or fixed
work
Thanks
j8chan
I've been trying to find a solution to my problem for a few days now. For
example, i have 8 people and 4 work stations, two people work with one
station so it becomes 4 teams.
i would like to level on both the pool of resources and the pool of work
stations but they have to by working together at the same time, I had two
tasks with each resource but it wouldn't schedule properly (ie a station
working without people at it). If one work stations goes down, then 2 people
can work on another different task for that resource pool.
Please help, could the answer lie in the task duration, fixed units or fixed
work
Thanks
j8chan