M
Marko
Hi,
I have an issue at my workplace:
It's not a problem assigning resources of known dates and durations, however
for my position (admin. based) I need to account for all my time during the
week. To do this, I've set up 6 or 7 tasks that I am working on during the
week (any task which I think I'll be booking time against), but obviously
it's not guaranteed, a) if I'll actually book time to that task, and b), how
much time I'll book. I simply want the ability to have a few tasks to book my
time against, which will total the given hours in the working day. For your
information, I just gave each task a duration of 60 days and a resource
allocation of 1% (so as to not overallocate myself.)
The problem is that when I book time to those tasks (using Project Web
Access), it seems to alter the remaining work available for the remaining
days in the week. The week after seems to reset itself. I can do a little
"post tweaking" to make the %ages look correct in MSP itself, but in the
resource allocation and PWA, the number of hours available for work actually
goes above the 7.4 hours allocated.
I've messed around with "fixed duration" and the other options, but can't
seem to get it to work.
Sorry for the ramble! but is there any simple way I can just allocate myself
as a resource against a few tasks, which I may or may not book my time
against all of them, but the time I split between some (or all) of them, adds
up to the working day, BUT doesn't have a knock on effect with the %ages and
hours available for the remainder of the week?
Any solutions, gratefully received! (But please make it simple as I'm an
MSP beginner!)
Thanks.
I have an issue at my workplace:
It's not a problem assigning resources of known dates and durations, however
for my position (admin. based) I need to account for all my time during the
week. To do this, I've set up 6 or 7 tasks that I am working on during the
week (any task which I think I'll be booking time against), but obviously
it's not guaranteed, a) if I'll actually book time to that task, and b), how
much time I'll book. I simply want the ability to have a few tasks to book my
time against, which will total the given hours in the working day. For your
information, I just gave each task a duration of 60 days and a resource
allocation of 1% (so as to not overallocate myself.)
The problem is that when I book time to those tasks (using Project Web
Access), it seems to alter the remaining work available for the remaining
days in the week. The week after seems to reset itself. I can do a little
"post tweaking" to make the %ages look correct in MSP itself, but in the
resource allocation and PWA, the number of hours available for work actually
goes above the 7.4 hours allocated.
I've messed around with "fixed duration" and the other options, but can't
seem to get it to work.
Sorry for the ramble! but is there any simple way I can just allocate myself
as a resource against a few tasks, which I may or may not book my time
against all of them, but the time I split between some (or all) of them, adds
up to the working day, BUT doesn't have a knock on effect with the %ages and
hours available for the remainder of the week?
Any solutions, gratefully received! (But please make it simple as I'm an
MSP beginner!)
Thanks.