Hi I am a project newbie. I ran into a situation below and wondering
if anyone can help. Here is the situation.
task1 part time supporting QA 20 days resourceX[30%]
task2 something else 5 days resourceX
task3 something else 4 days resourceX
task4 something else 2 days resourceX
the start and end date of task1 is dependant on some other tasks so
they may change. So what I want to do is for project to level so that
while resourceX is spending partial time on task1 I want project to get
resourceX to use the rest of the time on task2, 3, or 4.
The problem is Project doesn't overlap the tasks unless I explicitly
set resourceX [70%] for task2,3, or 4. So if I know when task1 is
going to start/end, then I can calculate which of the rest of the tasks
should be [70%]. But there is got to be a way for Project to
automatically utilize the other 70% of the time on task1 without me
explicitly specifying the percentage utilization for the rest of the
tasks. My real project is huge and start/end dates of task1
constantly changes. So I can't constantly recalculating which task
needs to have [70%] in order to overlap the tasks and fully utilize the
time.
I hope this makes sense and someone can help me. Thanks.
if anyone can help. Here is the situation.
task1 part time supporting QA 20 days resourceX[30%]
task2 something else 5 days resourceX
task3 something else 4 days resourceX
task4 something else 2 days resourceX
the start and end date of task1 is dependant on some other tasks so
they may change. So what I want to do is for project to level so that
while resourceX is spending partial time on task1 I want project to get
resourceX to use the rest of the time on task2, 3, or 4.
The problem is Project doesn't overlap the tasks unless I explicitly
set resourceX [70%] for task2,3, or 4. So if I know when task1 is
going to start/end, then I can calculate which of the rest of the tasks
should be [70%]. But there is got to be a way for Project to
automatically utilize the other 70% of the time on task1 without me
explicitly specifying the percentage utilization for the rest of the
tasks. My real project is huge and start/end dates of task1
constantly changes. So I can't constantly recalculating which task
needs to have [70%] in order to overlap the tasks and fully utilize the
time.
I hope this makes sense and someone can help me. Thanks.