Thanks for the tip....figured that I might as well document this for posterity:
Played around w/ both methods (% Complete, and Physical % Complete), didn't
really take to either....so ended up going down the route of developing custom
fields to calculate EV, SV, CV, SPI, CPI, EAC based upon % Work Complete.
(PV, AC were still ok as the default).
So far, on the Task level, this seems to be working. I then converted the
fields to Resource fields, and this I think is probably where I will get
the most bang for the buck...as now I can use the data to gauge performance
and/or estimating ability by Resource or by Department.
I wanted to take the calculations down to the assignment level, but here
I was stymied....as I can't figure out how to make a custom calculated field
on the assignment level in the Resource Usage View...my custom fields roll
up to the Resource and even the Departmental Group (w/ the exception of the
Flag fields), but they don't register on the Assignment - this despite the
fact that the built in MSP EV fields do seem to calculate Assignment data.
One other thing that I did for the Point-Based EVMS, was to:
1) Set up 2 X cost structures using 2 X rate tables: $1/h & $3/h
2) Assign the $3/h rate to critical path tasks to create an arbitrary weighting
system
3) Turn off the currency indicator, so you can't tell the EV calculations
are really using dollars - now they just look like numbers.
Hope that helps somebody.
-A