K
Kevin
Hi,
hope someone can help, the nature of my project and the groundwork done
means that I know all my tasks and start and finish dates, I am working to an
end date that cannot move. I have a lot of tasks that must occur
simulataneously and no matter what resources are required they will finish on
a certain date.
I have enetered tasks into Project 2003 and the start & finish dates for
each. The purpose being to make it easier to share and relay milestones +
highlight reports on activities and progress.
I now need to join them (the tasks) up to give me critical path etc and
demonstrate dependencies but whenever I do this Project auto finish starts
the tasks. This then impact the whole project.
They are not all FF, SF, SS or FS, some just overlap and simultaneous items.
I don't want to have to lag and lead each line to fit MS Project approach to
handling dependencies, it would take ages. Is there a way to make project
respect the dates for start and finish that I have enetered and not be too
clever, auto lagging or lead where necc but at all times preserve the dates
that I have enetered.
Many thanks,
hope someone can help, the nature of my project and the groundwork done
means that I know all my tasks and start and finish dates, I am working to an
end date that cannot move. I have a lot of tasks that must occur
simulataneously and no matter what resources are required they will finish on
a certain date.
I have enetered tasks into Project 2003 and the start & finish dates for
each. The purpose being to make it easier to share and relay milestones +
highlight reports on activities and progress.
I now need to join them (the tasks) up to give me critical path etc and
demonstrate dependencies but whenever I do this Project auto finish starts
the tasks. This then impact the whole project.
They are not all FF, SF, SS or FS, some just overlap and simultaneous items.
I don't want to have to lag and lead each line to fit MS Project approach to
handling dependencies, it would take ages. Is there a way to make project
respect the dates for start and finish that I have enetered and not be too
clever, auto lagging or lead where necc but at all times preserve the dates
that I have enetered.
Many thanks,