Problem with caledar...

V

Vit

hello to everybody,
I’m trying to set up the calendar on a old project, but unfortunately,
when I change the calendar, the schedule don’t change... (Project ->
Project Information... and change the calendar to the enterprise
calendar.... AND Task information -> Advanced and set up the calendar
for all the task... AND Tool -> options... -> Calendar and set up the
different start and finish hours....)
Everywhere I have set up the starts at 8 AM, but the task still start
at 7 AM...
What I’m doing wrong???? What are the different among every setting???
How can I avoid to use the minutes on the schedule??? (for example I
have a task that start for 11 minutes on Monday and continues for 3
hours and 49 minutes on Tuesday)....
Thanks so much to everybody...
Cheers
Vit
 
M

Mike Glen

Hi Vit,

Welcome to this Microsoft Project newsgroup :)

To begin with, you might like to see FAQ Item: 5. Default Working Hours.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top