I have a couple projects in which I linked all the tasks, and it set the
time line up as expected. Now if I go into them and modify the "work" of a
particular task, the task next in line does not adjust the start date
accordingly. The constraint type is "as soon as possible", but no matter
what I do with predecessors (even delete links altogether) the start date of
the task in question does not change. I can modify the start date by
actually changing the start date in the task information dialog, but I know
I've had this work properly in the past.
Any Clues???
TIA
Mike
time line up as expected. Now if I go into them and modify the "work" of a
particular task, the task next in line does not adjust the start date
accordingly. The constraint type is "as soon as possible", but no matter
what I do with predecessors (even delete links altogether) the start date of
the task in question does not change. I can modify the start date by
actually changing the start date in the task information dialog, but I know
I've had this work properly in the past.
Any Clues???
TIA
Mike