C
Chris
I am using Microsoft Office Project Professional 2003.
I have defined my project, added all the tasks with expected durations, and
organised all these tasks into phases. All the durations were calculated at
the planning stage based on a single resource working 100% of their time on
the task.
All the task are 'Fixed Unit' type and 'Effort Driven'.
I am now at the stage where I want to setup and assign the available
resources, and I have run into a couple of problems.
I am anticipating that a proportion of the resources assigned to the project
will be working at about 80% productivity. It seemed that the easiest way to
represent this information in Project was to open up the Resource Information
for the pertinent resources and change their 'Resource Availability' to 80%.
However, when I assign a resource with a lower than 100% availability to a
task, it does not adjust the duration accordingly. It seems to be making the
assumption that the duration was initially calculated with the lower
availability in mind. If you then change the resource to someone with a
different 'Resource Availability' it does change the duration. I had a read
through the help - and although I couldn't ascertain for certain, I believe
this is the intended behaviour?
I made the assumption this was the case, and tried an alternative approach.
I changed the Resource Availability back to 100% via the Resource Information
dialogue. On the Gantt Chart I then assigned this resource to the relevant
tasks. I then went back to the Resource Information and changed the Resources
Availability down to 80%. The task duration did not change - I had to
re-assign the same resource manually to get it to update correctly.
I couldn't find anyway of getting the task duration to update automatically
when changing the availability of a resource. I even tried levelling - and
this just reported it as an error.
I would be surprised if this was the expected behaviour? Can you recommend
an alternative approach, or an option I may be missing?
Many thanks,
I have defined my project, added all the tasks with expected durations, and
organised all these tasks into phases. All the durations were calculated at
the planning stage based on a single resource working 100% of their time on
the task.
All the task are 'Fixed Unit' type and 'Effort Driven'.
I am now at the stage where I want to setup and assign the available
resources, and I have run into a couple of problems.
I am anticipating that a proportion of the resources assigned to the project
will be working at about 80% productivity. It seemed that the easiest way to
represent this information in Project was to open up the Resource Information
for the pertinent resources and change their 'Resource Availability' to 80%.
However, when I assign a resource with a lower than 100% availability to a
task, it does not adjust the duration accordingly. It seems to be making the
assumption that the duration was initially calculated with the lower
availability in mind. If you then change the resource to someone with a
different 'Resource Availability' it does change the duration. I had a read
through the help - and although I couldn't ascertain for certain, I believe
this is the intended behaviour?
I made the assumption this was the case, and tried an alternative approach.
I changed the Resource Availability back to 100% via the Resource Information
dialogue. On the Gantt Chart I then assigned this resource to the relevant
tasks. I then went back to the Resource Information and changed the Resources
Availability down to 80%. The task duration did not change - I had to
re-assign the same resource manually to get it to update correctly.
I couldn't find anyway of getting the task duration to update automatically
when changing the availability of a resource. I even tried levelling - and
this just reported it as an error.
I would be surprised if this was the expected behaviour? Can you recommend
an alternative approach, or an option I may be missing?
Many thanks,