NA 1 d 5/26/04 5/26/04 5/26/04 36
Hello: someone has some inside knowledge about this
Take a look at the above: the first finish is project generated (from duration and start dates); the second is a custom date field created just to contain an imported finish date from xls. The third is a custom number w/ a projdatediff calc to show the difference between the two finish dates. What's up? Why is this showing a difference of one day (6 hr day shown in minutes), when there is no difference?
Hello: someone has some inside knowledge about this
Take a look at the above: the first finish is project generated (from duration and start dates); the second is a custom date field created just to contain an imported finish date from xls. The third is a custom number w/ a projdatediff calc to show the difference between the two finish dates. What's up? Why is this showing a difference of one day (6 hr day shown in minutes), when there is no difference?