Greetings to my favorite people. Again I need your
assistance to resolve the followings:
1. How do I resolve my resource usage not showing
accurate data. For instance I have someone slated for two
hours on one day and it shows him as being over allocated.
Even though the person is not listed elsewhere.
2. When I enter time in hours under work. My days shows a
mixture of decimal and whole days. How do I get MS Project
to be consistent and show 2hrs as.25d.
3. How do I set up a report to show resource usage in
weeks and a separate one in months (two separate reports).
Currently I only see the present week.
Any assistance provided will be appreciated. have a nice
day.
assistance to resolve the followings:
1. How do I resolve my resource usage not showing
accurate data. For instance I have someone slated for two
hours on one day and it shows him as being over allocated.
Even though the person is not listed elsewhere.
2. When I enter time in hours under work. My days shows a
mixture of decimal and whole days. How do I get MS Project
to be consistent and show 2hrs as.25d.
3. How do I set up a report to show resource usage in
weeks and a separate one in months (two separate reports).
Currently I only see the present week.
Any assistance provided will be appreciated. have a nice
day.