B
bschiek
This is driving me around the bend:
I am trying to link tasks to flow in a logical order on a 650+ task
project plan left behind by the terminated former manager. The same
resource is assigned at 100% to the 6 tasks I am trying to link. If I
highlight and link the tasks, the successor task turns into a
milestone! The task has a work value assigned, and that doesn't
change. Duration changes to 0. If I open the Task Info window, I can
uncheck the milestone box, but the task still has a work value, zero
duration and shows up as a split task on the Gantt chart. The task
constraint now becomes "Finish no later than" with the date that the
task should finish on if duration was calculated correctly. If I
change the constraint back to "As soon as possible", it goes back to a
milestone!
What am I doing wrong? ACK!
Thanks in advance.
Bruce.
I am trying to link tasks to flow in a logical order on a 650+ task
project plan left behind by the terminated former manager. The same
resource is assigned at 100% to the 6 tasks I am trying to link. If I
highlight and link the tasks, the successor task turns into a
milestone! The task has a work value assigned, and that doesn't
change. Duration changes to 0. If I open the Task Info window, I can
uncheck the milestone box, but the task still has a work value, zero
duration and shows up as a split task on the Gantt chart. The task
constraint now becomes "Finish no later than" with the date that the
task should finish on if duration was calculated correctly. If I
change the constraint back to "As soon as possible", it goes back to a
milestone!
What am I doing wrong? ACK!
Thanks in advance.
Bruce.