I try to change a date and the rest of the chart will not adjust to the new dates automatically
J John R McArthur Aug 13, 2007 #1 I try to change a date and the rest of the chart will not adjust to the new dates automatically
J Jim Aksel Aug 13, 2007 #2 F9 to recalculate. Tools/Options/Calculate automatic. You didn't key in dates manually did you??? -- If this post was helpful, please consider rating it. Jim It''s software; it''s not allowed to win. Visit http://project.mvps.org/ for FAQs and more information about Microsoft Project