S
svt4cobra6
Hi I have a task that I split because I need to assign different resources to
the task during different times, for example I have two summer hires so will
asign the task to them only through the summer and to someone else for all
other parts of the year. The task runs Jan 2011 to Jan 2012.
Thanks
the task during different times, for example I have two summer hires so will
asign the task to them only through the summer and to someone else for all
other parts of the year. The task runs Jan 2011 to Jan 2012.
Thanks