B
Bonnie
I have a question about leveling. Here is the situation:
I have two tasks, one that I would like the person to work on 50% a day for
2 days and the other is an 8 hour task that needs to fill in the rest of the
time. If I ...
1. enter the two tasks in project - assigned to a person to start on the
same day (both 8 hour tasks)
2. set the task type to fixed work (task type does not even seem to matter
with leveling)
3. Put the resource for the 1st task at 50% which spreads the task out over
2 days.
4. Hit leveling (Level now) allowing splits, etc. Project does not
effectively level the tasks and you get an overallocation of hours (12) on
the second day.
5. Could someone explain how to set the tasks up so this does not happen? In
many cases you may have a person who devotes 20% of there time a day to a
specific task and the remainder of time is for other things. Leveling does
not appear to spread the other hours appropriately.
I have two tasks, one that I would like the person to work on 50% a day for
2 days and the other is an 8 hour task that needs to fill in the rest of the
time. If I ...
1. enter the two tasks in project - assigned to a person to start on the
same day (both 8 hour tasks)
2. set the task type to fixed work (task type does not even seem to matter
with leveling)
3. Put the resource for the 1st task at 50% which spreads the task out over
2 days.
4. Hit leveling (Level now) allowing splits, etc. Project does not
effectively level the tasks and you get an overallocation of hours (12) on
the second day.
5. Could someone explain how to set the tasks up so this does not happen? In
many cases you may have a person who devotes 20% of there time a day to a
specific task and the remainder of time is for other things. Leveling does
not appear to spread the other hours appropriately.