Project Budget

A

AM

Can you track budget on Project with out manually typing it in in each row
and/or column?
 
J

JulieS

Hi AM,

From help:
===========================================
Cost is calculated based on the Standard Rate, Overtime Rate, Per Use Cost,
and Cost accrual settings for the resource and the amount of work assigned
to all resources for the task. Any fixed costs for the task are also added
to this field. As actual work or actual cost is reported on this task,
Microsoft Office Project 2003 calculates the cost by adding the actual cost
to the remaining cost
==============================================

If you have created resources with Standard Rate etc. and assigned them to
tasks Project will calculate the Cost. If you save a baseline you have a
baseline cost (budget) for your project. As you track actuals in the
project, Project calculates actual cost. No manual typing required.

I hope this helps. Let us know how you get along.
Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top