Hello,
I'm trying to customize a field on project level…
The field have to show if a project has been updated or not o the last
14 days…
I’m using Project Server 2003, Project Professional 2003 and PWA 2003.
Here you are the step that I have followed:
1) Opened Project Professional 2003
2) Opened Enterprise Global (Tool -> Enterprise Options -> Open
Enterprise Global)
3) Opened Enterprise Fields (Tool -> Customise -> Enterprise Fields…)
4) Selected “Project”
5) Selected “Text”
6) Inserted the following formula: IIf(DateDiff("d",[Last Update],
[Current Date])>=14,"Update Required","Current")
The problem is that the Project Fields Seems not to be updated….
On the PWA view, for example, there is the following information:
Project Test
Last Modified: 30/04/2008
Last Published: 30/04/2008
Custom Field: Updated Required
But today is the 8th of May, so it have to be “Current”!!!
I have check also on the Project Information (in Project Professional,
Project -> Project Information…), and unfortunately, the custom field
value is “Updated Required”…
What’s wrong??
Where can I check “Last Modified Date”, “Last Update Date” and “Last
Published Date” in Project Professional??
Thank you so much to every body will be able to help me…
Regards
Vit
I'm trying to customize a field on project level…
The field have to show if a project has been updated or not o the last
14 days…
I’m using Project Server 2003, Project Professional 2003 and PWA 2003.
Here you are the step that I have followed:
1) Opened Project Professional 2003
2) Opened Enterprise Global (Tool -> Enterprise Options -> Open
Enterprise Global)
3) Opened Enterprise Fields (Tool -> Customise -> Enterprise Fields…)
4) Selected “Project”
5) Selected “Text”
6) Inserted the following formula: IIf(DateDiff("d",[Last Update],
[Current Date])>=14,"Update Required","Current")
The problem is that the Project Fields Seems not to be updated….
On the PWA view, for example, there is the following information:
Project Test
Last Modified: 30/04/2008
Last Published: 30/04/2008
Custom Field: Updated Required
But today is the 8th of May, so it have to be “Current”!!!
I have check also on the Project Information (in Project Professional,
Project -> Project Information…), and unfortunately, the custom field
value is “Updated Required”…
What’s wrong??
Where can I check “Last Modified Date”, “Last Update Date” and “Last
Published Date” in Project Professional??
Thank you so much to every body will be able to help me…
Regards
Vit