While importing some project-files (Project 2002, non-
enterprise) to project 2003 server (enterprise projects),
I noticed that for some projects the actual work that has
been entered by the resources differs between imported
file and original files. The sum of actual work for the
task remains the same, but the hours are spread
differently. I need to keep the original values.
The redistribution happens when starting the import wizard
for enterprise projects (immediately after selecting the
file). Only some resources and tasks in some projects seem
to be affected. Most projects are OK.
I have already compared general, task-related and resource-
related settings but didn't find any significant
differences. What did I miss?
enterprise) to project 2003 server (enterprise projects),
I noticed that for some projects the actual work that has
been entered by the resources differs between imported
file and original files. The sum of actual work for the
task remains the same, but the hours are spread
differently. I need to keep the original values.
The redistribution happens when starting the import wizard
for enterprise projects (immediately after selecting the
file). Only some resources and tasks in some projects seem
to be affected. Most projects are OK.
I have already compared general, task-related and resource-
related settings but didn't find any significant
differences. What did I miss?