J
jgrafton
Does anyone else have this problem?
When I open a new project and start from scratch. I go to enter a Duration
of X amount of days, lets say 3 days. Then I enter in the Start Date of
5/1/2008, for example. The finish date that is calculated automatically ends
up being a majorly incorrect date. Instead of it populating the date as
being 3 days later, it randomly chooses a date and inserts it into the Finish
Date. So I end up w/ something like the following:
Duration Start Finish
3 days 5/1/08 5/16/08
Has anyone else had this problem? I have a service call in with Microsoft,
but if you could come up w/ a solution on here I would appreciate it,
jgrafton
When I open a new project and start from scratch. I go to enter a Duration
of X amount of days, lets say 3 days. Then I enter in the Start Date of
5/1/2008, for example. The finish date that is calculated automatically ends
up being a majorly incorrect date. Instead of it populating the date as
being 3 days later, it randomly chooses a date and inserts it into the Finish
Date. So I end up w/ something like the following:
Duration Start Finish
3 days 5/1/08 5/16/08
Has anyone else had this problem? I have a service call in with Microsoft,
but if you could come up w/ a solution on here I would appreciate it,
jgrafton