J
JC
I have a project, which has estimates, and then time phased actuals entered.
I was messing with an individuals calendar - changed it from a 6 hour per
day calendar to a 4 hour per day one to reflect us having less use of the
guy.
After doing this all my actuals which nicely added up to 5 days per week for
each person - for him they got mucked up. They still totalled 5 days per
week, except that one
week would be 4.26 and then the next would be 5.74, etc.
Why would project change the actuals? Surely the whole point of an actual is
that it actually happened and so project should keep it's nose out!!!
Help.
I was messing with an individuals calendar - changed it from a 6 hour per
day calendar to a 4 hour per day one to reflect us having less use of the
guy.
After doing this all my actuals which nicely added up to 5 days per week for
each person - for him they got mucked up. They still totalled 5 days per
week, except that one
week would be 4.26 and then the next would be 5.74, etc.
Why would project change the actuals? Surely the whole point of an actual is
that it actually happened and so project should keep it's nose out!!!
Help.