Project Resource Gap Analysis

I

ivorycl

Project has resources that have transferred or moved off to other initiative.
I want to determine the uncompleted task for the transferred resources and
prepared a customized report.
 
C

Catfish Hunter

If I understand the problem here is my suggestion: Add a new filter for that
specific resource: RESOURCE NAME EQUALS - xxxxxx and in the filter on line
two: AND - % Complete - IS LESS THAN - 100
Hope this helps.
 
J

Jan De Messemaeker

Hi,

Forgive me for bumping in.
I would filter on "contain" to include tasks with more than 1 resource.
HTH
 