Project Subtask Gant Bar

K

KC

When I create a new subtask, the bar in the Gant Chart is the same format as
the summary task. I can change the format of each subtask bar individually,
but I assume it should simply take the format I've established in the Bar
Styles dialogue box.

Any help is appreciated.

KCJ
 
J

JulieD

Hi KC

it should take the format you've set up in format/bar styles ...
you might like to select all your tasks and choose format / bar and press
the RESET button and see if this solves the problem.
(do on a copy of the project file just in case)
 