Is there a way of showing project tasks as Outlook tasks - not as Outlook
calendar entries??
 
J

JulieS

Hello Tog,

Are you using Project Server and Project Web Access? If so, please
repost your question to the Project Server newsgroup. If you are using
Project 2007 along with the Set Reminders feature, the tasks are added
as tasks in Outlook.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
C

Clint

Julie, what version of Project 2007 is needed to use "Set Reminders" feature?
I have the standard version and don't see it anywhere. Really would like to
figure out a way to have the dates show up and remind in outlook somehow.
Thanks!

p.s. Don't have the infrastructure to set up a server
 
J

JulieS

Hi Clint,

I believe it is in both the Standard and Professional version of
Project. Take a look at the Tracking toolbar and look for the little
bell.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top