Published Field

P

Pnina

Hello,

I have created an Enterprise Cost Field (Empty),
and given the resources the ability to update the
field from the PWA (Task Page).
They filled the field and updated the PM.
The PM gets the update and accepts it,But he doesn't see
the update at the project file ?

Any Idea ?

Pnina
 
D

Dale Howard [MVP]

Pnina --

The PM needs to insert the custom Cost field in one of the task Tables in
Microsoft Project Professional. A good candidate would be the task Cost
table (View - Table - Cost). Hope this helps.
 
G

Gary L. Chefetz \(MVP\)

Pnina:

Be aware that Enterprise task fields do not carry discreet values at the
assignment level, so the result is that this field will carry the value from
the last person who updated it, which can have unintended consequences if
you're assigning more than one resource to a task.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 
G

Guest

It doesn't work, i see 0.00.

-----Original Message-----
Pnina --

The PM needs to insert the custom Cost field in one of the task Tables in
Microsoft Project Professional. A good candidate would be the task Cost
table (View - Table - Cost). Hope this helps.







.
 
G

Guest

It doesn't work, I see only 0.00.
-----Original Message-----
Pnina:

Be aware that Enterprise task fields do not carry discreet values at the
assignment level, so the result is that this field will carry the value from
the last person who updated it, which can have unintended consequences if
you're assigning more than one resource to a task.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-



.
 
Top