PWA 2007 and Project Pro Work Hours discrepancy

M

Maurizio

Hi,

When I open a schedule in Project Pro the WORK field hours are different
from the view in PWA. Have been notincin a great deal of discrepancies with
several schedules. It is safe to point out that the schedules have been
synchronized accrodingly and the updates have been published.

Has anyone encountered this issue? I understand that SP1 took care of the
ACTUAL WORK issue.

Any feedback is greatly appreciated!
 
S

Spencer Lamoreaux

I would double check that you are comparing PWA to the assignments
(not tasks) in MS Project Pro. Look at the Resource Usage or Task
Usage view to make sure that the assignment level work is the same as
the PWA work. If there is still a discrepency, I would go in as an
admin and delete the published version of the project and then re-
publish the Gantt from Project Pro.

Hope that helps.

Spencer Lamoreaux
AGIS Consulting
Intel IT Scheduling Product Manager
 
M

Marc Soester [MVP]

Maurizio,

I would check if you have any jobs in the queue that may have not been
processing.
 
Top