PWA - How to Collapse all tasks... ?

P

Pablo

Hi, I'm recently using PWA and can't figure out a way to collapse all
tasks I have assigned.

In the standard version of MS Project I can use the "Collapse All"
funcion. Is there a similar functionality for PWA ?

Thanks,

Pablo
 
M

Mike Glen

Hi Pablo,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 