my client was assigned to the default project manager group in project server
2007, he created a project assigned some tasks to himself, but these yasks do
not dispaly at all in project server, he can't view them under My Tasks in
PWA
 
D

Dale Howard [MVP]

jummy --

In the future, please post your Project Server 2007 questions to the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
the most likely causes for the problem are:

1. The PM did not publish the project using File - Publish. Tasks do not
show up on the team members' My Tasks page until the PM publishes the
project.

2. If the PM did publish the project, then he may have set the Booking type
value to Proposed in the Build Team dialog (click Tools - Build Team from
Enterprise and set the Booking value to Committed, and then publish again).

3. The My Tasks page shows only Current Tasks by default and the tasks in
question are too far in the future to qualify as Current Tasks (normally 10
days in the future). The user can click the Settings pick list menu and
select the View Options item on the list, and then deselect the Show only
current tasks item and click the Apply button.

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top