PWA - Task Update Page problems

C

Claudia

We would like to set the working week to start from Monday, we set
that information in Admin - Customize Web Access - Tracking settings.
The timeperiod in the timesheet is "weekly" and the time spanning is
"2 weeks".

Everything seems to work fine in the Resources TimeSheet View, the
week starts on Monday and ends on sunday. The resource inserts some
hours only for the first week of the month and sends the update to the
manager.
When the manager goes to per "Update" Web Page sees what follows:
The week starts on monday and ends on saturday and then we have one
single column with some hours for the remaining sunday!
Instead we were expecting to see one single period with the total
amount of hours declered by the resource!
Can some one help or explain?

Thanks

Claudia
 