First of all, sorry about my poor english.
I have Ms Project 2000 version in Portuguese.
I am trying to see the QTC (cost after de actual date) but Ms Project is
showing cost before the actual date. The acumulated cost is correct, but the
distribution showed is not after the actual date.
Follow the configurations used:
Activity type: Work fixed
Options: Ms Project do not calculate real cost.
Total cost modifications will be extended to actual date
Modifications on % concluded will be extended to actual date
I have Ms Project 2000 version in Portuguese.
I am trying to see the QTC (cost after de actual date) but Ms Project is
showing cost before the actual date. The acumulated cost is correct, but the
distribution showed is not after the actual date.
Follow the configurations used:
Activity type: Work fixed
Options: Ms Project do not calculate real cost.
Total cost modifications will be extended to actual date
Modifications on % concluded will be extended to actual date