H
Hytekjunky
Task are set @ Fixed work (hours). Resource A set as material. Resource B
set as Work.
Is there a way to enter the number of Resource A that has been completed
instead of having to enter percentages? Example. Resource "Conduit" has 500
feet assigned to Task 1. During the previous work day, 250 feet of conduit
was installed/completed. Is there a way to enter the quantity of conduit
completed instead of the percentage completed or hours worked? If so, by
entering an updated quantity, will Project update the percentage for me?
TIA,
Me
set as Work.
Is there a way to enter the number of Resource A that has been completed
instead of having to enter percentages? Example. Resource "Conduit" has 500
feet assigned to Task 1. During the previous work day, 250 feet of conduit
was installed/completed. Is there a way to enter the quantity of conduit
completed instead of the percentage completed or hours worked? If so, by
entering an updated quantity, will Project update the percentage for me?
TIA,
Me