J
Jon Baldan
We have an existing project which has been baselined with some costs.
Actuals have been recorded against this project previously. This
project spans a financial year boundary and new costs for the
resources have been published for the new financial year. We want to
re-baseline with these new costs but without adjusting the original
duration (i.e. work out how much extra the project would cost based on
the original duration and hours, not the current hours adjusted by the
actuals being recorded). Note that we require to leave our cost per
hour the same before the financial year boundary and only update it
for the hours baselined for after the financial year boundary.
We would appreciate any input from people who have had similar issues.
We would imagine that Professional Services firms would go through
this on at least a yearly basis.
Thanks in advance
Actuals have been recorded against this project previously. This
project spans a financial year boundary and new costs for the
resources have been published for the new financial year. We want to
re-baseline with these new costs but without adjusting the original
duration (i.e. work out how much extra the project would cost based on
the original duration and hours, not the current hours adjusted by the
actuals being recorded). Note that we require to leave our cost per
hour the same before the financial year boundary and only update it
for the hours baselined for after the financial year boundary.
We would appreciate any input from people who have had similar issues.
We would imagine that Professional Services firms would go through
this on at least a yearly basis.
Thanks in advance